CSoT finished its 6-Gen T4 Hubei line building construction

In June 2017 CSoT launched the construction of its new Wuhan 6-Gen AMOLED fab (the T4 fab). This $5 billion fab is expected to begin production in Q2 2019, with full mass production achieved by 2020. The fab's capacity will be 45,000 substrates per month, and it will be used to make small and medium-sized flexible and foldable OLEDs.

CSoT Wuhan 6-Gen AMOLED fab ceiling ceremony (Dec 2017)

Yesterday CSoT held a ceremony to mark the building main concrete structure complete - 13 days ahead of schedule and 153 days since the beginning of construction. The next steps will be the construction of the clean rooms and moving in the equipment.